![]() Aberdeen City Hall 123 S Lincoln St Aberdeen, SD 57401 View Power Point Presentation |
COMMUNITY OVERVIEW
STATE
OF SOUTH DAKOTA JANUARY-FEBRUARY
2002
Tony
Mendes, ND & SD POC Contact, FEMA, Region VIII, 303-235-4790 Lynne
Rath, SD POC, SD DEM, Pierre, SD 605-773-3231
ABERDEEN, SOUTH DAKOTA REPORT For
more information, contact: Robin
Bobzien, Aberdeen, SD PI POC, 605-626-7017
Vernon
H Meyer, Aberdeen, SD PI Coordinator, 605-626-7017
MEMORANDUM OF AGREEMENT SIGNED: December 2, 1998 ABERDEEN,
SD – Current
Activities –
February - 2002 §
South Aberdeen
Drainage Projects: 1.
South-West Drainage Project:
The Contractor, Dahme Construction Inc.,began construction on December 7, 2001. Work has proceeded on all three facets of the project: 4,434 feet of storm sewer, 2178 feet of force main and excavating a 362,170 cubic yard holding pond. As of February 12, 2002, 4,593 lineal feet of 60-inch reinforced concrete storm sewer pipe and 2,150 lineal feet of 18-inch force-main have been installed. Approximately 233,000 cubic yards have been excavated for the holding pond. Due to the high water table in this area, temporary pumps were installed to dewater so excavation can proceed. The valve pit as well and wet well have been installed. A 10 Hp and 60 Hp pump have been installed in the wet well. Inlet and discharge pipes remain to be connected. Construction expenditures so far have been about $1,438,410. The winning bid for the total project was $2,903,826.46. The City and the FEMA Hazard Mitigation Grant Program (HMGP) will fund it. FEMA will provide $1.5 million and the City will fund the remainder of the project. 2. South-East Drainage Project: The
City is currently working on designing a new storm sewer for flood prone
areas of south Lincoln and south Main Street. §
North Aberdeen
Drainage Projects: 1.
Northwest Storm
Water Detention Basin:
The Storm Water Management Plan suggested solution for the
northwest Aberdeen involves a number of
components: A. Increasing the capacity of the existing “Conlin Holding Pond” B.
Replace and/or
install new gravity storm sewer to holding pond and C.
Install a new 12-inch
force main from holding pond to Foot Creek. The
initial project will be to increase the holding pond capacity by making
the existing pond deeper. This
will add approximately 17.5 acre-feet of storm water storage.
Existing inlets and outlet will also be replaced with new
structures. Bids
for this project were opened January 30, 2002.
Dahme Construction Company was the low bidder at $118,521.15 and
was awarded the contract on February 4 at the City Commission meeting. 2. Piping & Lift Stations for the above projects: Dates for a bid opening are scheduled for sometime in
March or April 2002. §
Northeast Flood
Control Project:
All land needed to construct Phase II of the Aberdeen Flood Control
Project has been purchased. After
title insurance has been obtained, the project can then be bid. § Moccasin Creek Low-Flow Channel Project: The Colorado consultant, INTERFLUVE, is in the process of determining the feasibility of changing Moccasin Creek channel cross section to facilitate better transport of sediment during low water flows. A representative of INTERFLUVE was in Aberdeen on January 15 to review existing conditions on Moccasin Creek. The preliminary design and recommendations shall be completed by March 1, 2002. A grant of up to $5,000 from the State of South Dakota is available for this work. |
||
|
|